How Trump’s Speed-to-Power Push for Data Centers Could Backfire



The Trump administration is trying to ease data centers’ power permitting burden. It’s likely to speed things up. Whether it’ll kick up more dust for the industry is literally up in the air.

On Tuesday, the EPA proposed a rule change that would let developers of all stripes start certain kinds of construction before getting a historically necessary permit under the Clean Air Act. Right now this document known as a New Source Review has long been required before you can start building anything that will release significant levels of air pollutants – from factories to natural gas plants. If EPA finalizes this rule, it will mean companies can do lots of work before the actual emitting object (say, a gas turbine) is installed, down to pouring concrete for cement pads.

The EPA’s rule change itself doesn’t mention AI data centers. However, the impetus was apparent in press materials as the agency cited President Trump’s executive order to cut red tape around the sector. Industry attorneys and environmental litigants alike told me this change will do just that, cutting months to years from project construction timelines, and put pressure on state regulators to issue air permits by allowing serious construction to start that officials are usually reluctant to disrupt.

“I think the intended result is also what will happen. Developers will be able to move more quickly, without additional delay,” said Jeff Holmstead, a D.C.-based attorney with Bracewell who served as EPA assistant administrator for air and radiation under George H.W. Bush. “It will almost certainly save some time for permitting and construction of new infrastructure.”

Air permitting is often a snag that will hold up a major construction project. Doubly so for gas-powered generation. Before this proposal, the EPA historically was wary to let companies invest in what any layperson would consider actual construction work. The race for more AI infrastructure has changed the game, supercharging what was already an active debate over energy needs and our nation’s decades-old environmental laws.

Many environmental groups condemned the proposal upon its release, stating it would make gas-powered AI data centers more popular and diminish risks currently in place for using dirtier forms of electricity. Normally, they argue, this permitting process would give state and federal officials an early opportunity to gauge whether pollution control measures make sense and if a developer’s preferred design would unduly harm the surrounding community. This could include encouraging developers to consider alternate energy sources.

“Inevitably agencies have flexibility as to how much they ask, and what this allows them to do is pre-commit in ways that’ll force agencies to take stuff off the table. What’s taken off the table, it’s hard to know, but you’re constraining options to respond to public concerns or recognize air quality impacts,” said Sanjay Narayan, Sierra Club’s chief appellate counsel.

Herein lies the dilemma: will regulatory speed for power sacrifice opportunities for input that could quell local concerns?

We’re seeing this dilemma play out in real time with Project Matador, a large data center proposal being developed in Amarillo, Texas, by the Rick Perry-backed startup Fermi Americas. Project Matador is purportedly going to be massive and Fermi claims its supposed to one day reach 11 GW, which would make it one of the biggest data centers in the world.

Fermi’s plans have focused on relying on nuclear power in the future. But the only place they’ve made real progress so far in getting permits is gas generation. In February, the Texas Commission on Environmental Quality gave Fermi its air permit for building and operating up to 6 gigawatts of gas power at Project Matador. At that time, Fermi was also rooting for relaxed New Source Review standards, applauding EPA in comments to media for signaling it would take this step. The company’s former CEO Toby Neugebauer also told investors on their first earnings call that Trump officials personally intervened to help get them gas turbines from overseas. (There’s scant public evidence to date of this claim and Neugebauer was fired by Fermi’s board last month.)

But now Fermi’s permit is also being threatened in court. In April, a citizens group Panhandle Taxpayers for Transparency filed a lawsuit against TCEQ challenging the validity of the permit. The case centers around whether the commission was right to deny a request for a contested case hearing brought by members of the group who lived and worked close to Project Matador. “Once these decisions are made, they don’t get reversed,” Michael Ford, Panhandle Taxpayers for Transparency’s founder, said in a fundraising video.

This is also a financial David vs. Goliath, as Ford admits in the fundraising video they have less than $2,000 to spend on the case – a paltry sum they admit barely covers legal bills. We’re also talking about a state that culturally and legally sides often with developers and fossil fuel firms.

At the same time, this lawsuit couldn’t come at a more difficult time as Fermi is struggling with other larger problems (see: Neugebauer’s ouster). Eric Allman, one of the attorneys representing Panhandle Taxpayers for Transparency, told me they’re still waiting on a judge assignment and estimated it’ll take about one year to get a ruling. Allman told me legally Fermi can continue construction during the legal challenge but there are real risks. “Applicants on many occasions will pause activity while there is an appeal pending,” he told me, “because if the suit is successful, they won’t have an authorization.”

Aerial photos reported by independent journalist Michael Thomas purportedly show Fermi hasn’t done significant construction since obtaining its air permit. Fermi did not respond to multiple requests for comment on the lawsuit.

Industry attorneys I spoke to who wished to remain anonymous told me it was too early to say whether EPA’s rulemaking would exacerbate local conflicts by making things move faster. “A lot of times the environmental community likes to litigate things in the hope delays will kill a project, so in that regard, this strategy may be harder for them to implement now,” one lawyer told me. “But just because a plant gets a permit doesn’t mean they can build.”

Environmental lawyers, meanwhile, clearly see more potential for social friction in a faster process. Keri Powell of the Southern Environmental Law Center compared this EPA action to xAI’s rapid buildout in Tennessee and Mississippi where the Al company’s construction of gas turbines before it received its permits has only added to local controversy. This new rule would not make what xAI did permissible; this is a different matter. Yet there are thematic similarities between what the company is doing and the new permitting regime, with natural gas generation expanding faster when companies are allowed to start forms of site work before an air permit is issued.

“By the time a permit is issued, the company will be very, very far along in constructing a facility. All they’ll need to do is bring in the emitting unit, and oftentimes that doesn’t entail very much,” she said. “Imagine you’re a state or local permitting agency – your ability to choose something different than what the company already decided to do is going to be limited.”


It’s worth noting EPA insists nothing in this proposal should be construed as giving room for companies to pressure regulators into issuing permits. The agency did not respond to a request for additional comment.