Permitting on Federal Land Has Long Been a Headache



This week’s conversation is with Elizabeth McCarthy of the Breakthrough Institute. Elizabeth was one of several researchers involved in a comprehensive review of a decade of energy project litigation – between 2013 and 2022 – under the National Environment Policy Act. Notably, the review – which Breakthrough released a few weeks ago – found that a lot of energy projects get tied up in NEPA litigation. While she and her colleagues ultimately found fossil fuels are more vulnerable to this problem than renewables, the entire sector has a common enemy: difficulty of developing on federal lands because of NEPA. So I called her up this week to chat about what this research found.

The following conversation was lightly edited for clarity.

So why are you so fixated on NEPA?

Personally and institutionally, [Breakthrough is] curious about all regulatory policy – land use, environmental regulatory policy – and we see NEPA as the thing that connects them all. If we understand how that’s functioning at a high level, we can start to pull at the strings of other players. So, we wanted to understand the barrier that touches the most projects.

What aspects of zero-carbon energy generation are most affected by NEPA?

Anything with a federal nexus that doesn’t include tax credits. Solar and wind that is on federal land is subject to a NEPA review, and anything that is linear infrastructure – transmission often has to go through multiple NEPA reviews. We don’t see a ton of transmission being litigated over on our end, but we think that is a sign NEPA is such a known obstacle that no one even wants to touch a transmission line that’ll go through 14 years of review, so there’s this unknown graveyard of transmission that wasn’t even planned.

In your report, you noted there was a relatively small number of zero-carbon energy projects in your database of NEPA cases. Is solar and wind just being developed more frequently on private land, so there’s less of these sorts of conflicts?

Precisely. The states that are the most powered by wind or create the most wind energy are Texas and Iowa, and those are bypassing the national federal environmental review process [with private land], in addition to not having their own state requirements, so it’s easier to build projects.

What would you tell a solar or wind developer about your research?

This is confirming a lot of things they may have already instinctually known or believed to be true, which is that NEPA and filling out an environmental impact statement takes a really long time and is likely to be litigated over. If you’re a developer who can’t avoid putting your energy project on federal land, you may just want to avoid moving forward with it – the cost may outweigh whatever revenue you could get from that project because you can’t know how much money you’ll have to pour into it.

Huh. Sounds like everything is working well. I do think your work identifies a clear risk in developing on federal lands, which is baked into the marketplace now given the pause on permits for renewables on federal lands.

Yeah. And if you think about where the best places would be to put these technologies? It is on federal lands. The West is way more federal land than anywhere else in the county. Nevada is a great place to put solar — there’s a lot of sun. But we’re not going to put anything there if we can’t put anything there.

What’s the remedy?

We propose a set of policy suggestions. We think the judicial review process could be sped along or not be as burdensome. Our research most obviously points to shortening the statute of limitations under the Administrative Procedures Act from six years to six months, because a great deal of the projects we reviewed made it in that time, so you’d see more cases in good faith as opposed to someone waiting six years waiting to challenge it.

We also think engaging stakeholders much earlier in the process would help.