How to Build a Wind Farm in Trump’s America

It turns out that in order to get a wind farm approved in Trump’s America, you have to treat the project like a local election. One developer working in North Dakota showed the blueprint.
Earlier this year, we chronicled the Longspur wind project, a 200-megawatt project in North Dakota that would primarily feed energy west to Minnesota. In Morton County where it would be built, local zoning officials seemed prepared to reject the project – a significant turn given the region’s history of supporting wind energy development. Based on testimony at the zoning hearing about Longspur, it was clear this was because there’s already lots of turbines spinning in Morton County and there was a danger of oversaturation that could tip one of the few friendly places for wind power against its growth. Longspur is backed by Allete, a subsidiary of Minnesota Power, and is supposed to help the utility meet its decarbonization targets.
Except by the time the zoning officials’ decision came before the full county commission, the winds were once again blowing at Longspur’s back and county officials denied the denial. Then a few weeks later, the zoning board reconsidered Longspur and opted to approve it. Now Longspur has the permits it needs from the county.
“They have the right to put the towers on their land,” Morton County commission vice chair Jackie Buckley told me. “And Longspur has crossed their Ts and dotted their Is.”
I investigated what happened here and it turns out, Allete saw what happened at the hearing and worked extremely hard to bring supporters out when the zoning officials’ decision came before the full Morton County commission. They brought with them a bevy of landowners with a future Longspur turbine sited on their property to speak, so many that it severely outnumbered the opposition. One after another, residents spoke out against the anti-wind naysayers, a phenomenon I rarely see in fights over renewable energy projects in the United States. One resident called the wind turbines “a windfall” that was ensuring their family’s “retirement plans.” Another compared it to neighbors denying a farm the right to build a barn. Multiple people said if coal mining could happen in Morton County, why couldn’t wind?
“We just tried to understand, even internally. We asked, ‘Why didn’t we have more proponents speaking?’” Todd Simmons, Allete’s vice president of generation operations, told me in an interview this week about the project’s initial rejection. He said after the initial zoning rejection, the company then went door to door asking supporters to come testify. “We tried to make sure that landowners knew that you may have to show up and be more than present. We wanted a civil meeting, and we did not want an argumentative meeting, [but] they were not coached.”
Candidly, this style of outreach reminds me a lot of door-to-door campaign canvassing and a well-worn phrase in professional politics: it all comes down to turnout. And Allete treated the situation that way, telling me that the initial rejection to them was because of an absence, not conflict. “When the folks who were anti- spoke, and the rest of the crowd did not say anything, there was a belief that silence was [an] agreement by the rest,” Simmons told me.
Buckley told me that some of these supporters were actually at the zoning hearing too, but did not want to speak up because “they wouldn’t talk against their neighbor.” Out in rural communities like Morton County, “they all know each other – it’s all one neighborhood community.” In the end, the county commission felt it couldn’t deny people’s property rights, let alone invite whatever legal ramifications would arrive from denying the project in spite of the support from these property owners. “I think it had to do more with private property rights and the people that were in favor of it have property rights, same as do the people in opposition,” Simmons said.
I think there’s an important conclusion to be drawn from what happened in Morton County for any renewable energy project developer out there dealing with local opposition. Too often I watch and listen to local permitting hearings where the dissenting voices are the only ones raised. There are obvious risks for anyone in a small community who does speak up, as I’ve heard of threats against people who come out in support of a project, from anti-renewables homeowners. But it’s clear from what happened to Longspur there is strength in numbers when supporters are mobilized to speak up.
Allete told me they saw an education in the Longspur permitting process too. “It doesn’t matter where you’re building,” SImmons said. “Working with the landowners, and the public agencies…. The sooner you can help them understand what the project is actually about, the better you are.”